News
-
March 2025Permit application for wastewater treatment plantCompletion of park conceptWork on the facade continues
-
Fernuary 2025Cleaning of the eastern facade beginsRestoring the eastern window openingsInspection day
-
January 2025Work plan for 2025Cleaning the castle surroundings
-
December 2024Scaffolding moved to the western facadeWork on the park conceptDemolition of the basement wall
-
November 2024All western wing windows installedRepair of the eaves of the eastern roof
-
October 2024Installing first ground floor windowsThe solution for a basement wall removaldiv>September 2024Approval of all windowsWestern facade restoration completeCleaning of the reservoir and the surroundingsAugust 2024National Uprising celebrations, Guided toursCleaning the parkWater pipline leak repairedJuly 2024Restoring the original shape of window openingsAll roof windows installedFacade colour selectedJune 2024The restoration of the facade continuesHeating method choicesRoof windows productionMay 2024Ecological wastewater treatment project preparationWindows for the roof approvedVisit from the primary school KuneradApril 2024The cleaning of the facade has begunSample custom-made windows installedMarch 2024Some of the original furniture was foundPlanning the facade restorationAuthorities approved the roofFebruary 2024Planning an ecological waste-water-treatment plantBudget for 2024January 2024A window supplier selectionWater supply repairGovernment grant settlement
-
December 2023Completion of the last roof repairsThe roof is complete!Planning for the year 2024
-
November 2023Two glass towersRoof insulation and plasterboardFireproof coatingsRequest for approval of the roof
-
October 2023Days of architectureLightning rod installationInspection of hydrantsSlate laying almost complete
-
September 2023The first glass towerWorks on the internal roof insulationTemporary staircase
-
August 2023Work on the roof continuesInspection and cleaning of sewersRepair of the water source fencingOpen door day
-
July 2023Carpenters finished the east roofThe facade between the E and W roofCleaning up overgrown greenery in the park
-
June 2023Carpenters and slaters continue in full swingCleaning of original chimneysThe last turrets of the eastern roof
-
May 2023Two new dormers in the atticRepairs to the basement wallsFinishing the main chimney
-
April 2023Carpenters continue on the eastern roofThe first slate on the eastern roofRemoval of basement floors
-
March 2023Construction of the eastern roof turretsThe first chimney is readyRemoval of plaster in interiorsTree condition check in the park
-
February 2023First eastern roof dormersRoof slating continues200-years old linden tree fell
-
January 2023Works on the cottage startingCarpenters work in the interiorClearing the drinking water well surroundingsPlans for 2023
-
December 2022Collapsed inner pillar repairedChristmas break
-
November 2022Completion of the east roof trussPreparing the castle for winter
-
Oktober 2022Work on the east roof trussWork on the first turretPartial collapse of an inner pillar
-
September 2022Completion of the west roof trussUnderpinning of the foundations completedRain slows us down
-
August 2022The first structures of the eastern roofThe first slate on the western roofCompletion of stone cladding restoration
-
July 202214 dormers of the west roof completedPreparation of east roof structures in workshopsStatic interior modifications necessary for the roof construction
-
June 2022Construction of the west roof wooden structuresDrinking water permit granted2nd phase of the stone cladding restoration
-
May 2022The first metal structures are on the roofCleaning the park
-
April 2022Underpinning the foundationsPreparation of roof structuresSelection of the roof construction supervisor
-
March 2022Deepening of the ground floorConstruction of scaffolding around the entire castleThieves on the building site
-
February 2022Preparation of the space for the staircase and liftFinalize details for the roof constructionLarge window repair
-
January 2022Redrawing the plans
-
December 2021Government grant for the roof receivedTerraces and staircase insulation completeDocuments for the water permit submitted
-
November 2021Signed the contract with the roof supplierResults of the hydrogeological survey
-
October 2021Public tender results for the roof supplier announcedTerraces and external staircase restoration continues
-
September 2021Public tender for the roof constructionWater reservoir maintenance
-
August 2021Yield test of the drinking water wellUprising celebrations in the castle parkOpen for visitors for one day
-
July 2021Park greenery treatment
-
June 2021The stone cladding restoration continuesProject for the small house restoration
-
May 2021The stone cladding restoration startsCastle's outbuilding roof repairs
-
April 2021Resolved the ownership to the well and reservoirPreparation of the yield test for the water wellProject for stairs and elevator building adjustments
-
March 2021Work on the final reconstruction projectThe castle’s water system condition check
-
February 2021Monuments office assessment of the park survey resultsImplementation project for roof renovation
-
January 2021Assessing of the various heating system options
-
December 2020Castle’s water supply/processing archive researchPro Monumenta inspection report
-
November 2020Castle ready for the winter
-
October 2020Temporary roof completed
-
September 2020All 3 floors’ ceilings completedThe turret rebuild completedTemporary roof project approved
-
August 2020SNP celebrationsFor one day we opened to public
-
July 2020Stabilization of the falling terraceTurret and more ceilingsPro Monumenta inspectionTemporary roofing projectRepairs on the SNP Memorial
-
June 2020The electricity is connectedPreparation of the 2nd floor ceilingsWork on the final reconstruction projectInspection day with Monuments office
-
May 2020Preparation work for the power supplyGround floor ceilings completeLaunch of the website and social mediaPlans for the remaining rescue works
-
April 2020
Works on the ground floor ceilingInspection dayStone cladding needs immediate attention
-
March 2020Restrictions due to coronavirusGround floor ceiling plansPower company proposed a way to connectCleaning completed - extracted 1200 tons of rubble
-
February 2020
The castle can be entered safelyFirst sketches of the final restoration projectInspection dayThe restoration of SNP Memorial discussed with OZ AKURADMedia interest continues
-
January 2020310 tons of rubble have already been removedRemoval of dangerous ceilingsProblems with electricity connection
-
December 2019
Media interest continuesTheft of the castle stairsMeeting with the mayor and OZ AKURAD
-
November 2019Discussion of the first steps with the Monument officeStructural assessment - the castle remains without a roofCooperation with the construction company RBRing beginsPreparation of the castle surroundingsStatue of St. Štefan exhibited at the Monument office
-
October 2019
Contact with Count of BallestremFirst meeting with the Monument officeAgreement with University of Žilina on the digitalizationBalustrades and land cleaningGeodetic measurements
-
September 2019Handover of the castle and documentationThe first media and family reactionsAssessment of the castle’s condition by specialistsStudying all available information about the castle
-
August 2019
Simple website launch